Evaluation and award: what happens after you submit
How committees examine bids, how the ranking is calculated, and how to read an award result.
Niger edition: the rules shown are this country's.Change country
Once the packages are opened, your bid disappears into a committee and you often hear nothing for weeks, sometimes months. That silence is normal, but your work does not stop: the committee can write to you at any moment, and a late reply can eliminate you. Here is what happens in that time, in order, and what you have to do.
What the committee does, in order
The evaluation committee applies the grid and the criteria written in the tender file, and nothing else. The usual order is as follows.
Administrative compliance
Are the required documents there, valid and signed? Does the bid security comply? This is where expired certificates and missing forms fall. In some files the committee accepts that a non-essential document be supplied afterwards. Do not count on it.
Technical review
Does your bid answer what was asked? The committee checks the eliminatory criteria, references, staff, equipment and schedule, and gives a score if the file provides for one. Often, a bid that does not reach the technical minimum never has its price looked at.
Financial review
The committee redoes the sums, corrects errors, adjusts prices so they can be compared, applies any preferences and looks for abnormally low bids.
Ranking and final check
It ranks the bids and proposes a winner. Some files provide at this stage for a closer check of the top-ranked firm: financial capacity, references, sometimes a visit. If it fails, the committee moves to the next one.
After the committee's opinion, the award often goes through a validation: an oversight body or the funder's no-objection, depending on the contract. That is one reason the result can take time.
Lowest evaluated bid or weighted score
The file says which of these two methods applies. Works, supplies and ordinary services most often use the first, and consulting the second.
The lowest evaluated bid. Among the bids that meet the requirements, the contract goes to the one with the lowest evaluated price. The evaluated price can differ from the price read aloud: error corrections, adjustments, preferences. A high technical score earns nothing extra here. You just have to clear the bar.
The weighted score. The committee scores technical quality and price, then combines them using the weights written in the file. The best combined score wins, even without the lowest price. This is the classic consulting case, with a financial envelope opened only for those who reached the minimum technical score.
After a consulting ranking, the contract is generally negotiated with the top-ranked firm. In a classic tender, negotiating the price is usually forbidden. With private companies and some organisations, on the other hand, it can be common: see Who is buying and which rules apply.
If the committee writes to you
The committee can ask for a clarification: an unreadable document, a date to confirm, a reference to clear up. The request comes in writing and gives a time limit, often very short.
- Reply at once, and in writing. Watch the e-mail address and phone number you gave in the bid, including when travelling. A late reply can be treated as no reply.
- Reply only to what is asked. You are clarifying your bid, not writing a better one.
- You cannot change your price, or anything that would change the substance of the bid. The only usual price change is the committee's correction of a calculation error.
Do not try to reach committee members privately either. Any attempt to influence them can get your bid rejected, and bring heavier sanctions.
Preferences and abnormally low bids
Some rules grant a preference, for example to national, regional or local firms, or to small businesses. It often takes the form of a margin applied only for the comparison: the foreign competitor's price is raised for the calculation, and the contract is then signed at your real price. If you qualify, attach what the file asks for to prove it, because it is not always applied automatically.
If your price seems abnormally low, the committee can ask you to justify it. Have your quotes and price breakdown ready: see Price your financial bid.
Evaluating bids
- A tender selects the lowest evaluated compliant bid, without negotiation, on criteria known in advance and expressed in money terms. If the authority uses a single criterion, it is price. Criteria can include running costs, technical value, after-sales service, delivery time or payment schedule (art. 29, 111). The qualification of the lowest-evaluated bidder is checked independently of the content of its bid (art. 29).[1]
- The evaluation commission reports within 5 calendar days of receiving the files and the opening report, and up to 14 days for complex contracts. An abnormally low bid may be rejected by reasoned decision, but only after the bidder has been invited to justify its price in writing. A variant is considered only if the dossier allows it (art. 109, 113; order no. 0019, art. 11).[1][4]
Preferences and SMEs
- A preference may be given to the bid of a national or community firm, expressed as a percentage of the bid amount and capped at 15%. It may also apply to a firm offering products of national or community origin, or committing to subcontract to national firms. It can be claimed only if the tender dossier provides for it. An extra 5% preference goes to craft enterprises and artisans established in the UEMOA area. For contracts paid from own funds, the authority may reserve a percentage for national SMEs in its procurement plan (art. 112).[1]
Extending bid validity
Your bid is valid for a period set by the file. If the evaluation runs past that period, the buyer can ask you to extend it.
Take this request seriously and reply within the time given. As a general rule:
- you can refuse, and you then leave the competition without losing your security;
- if you accept, you keep your price unless a clause says otherwise, and you must have the bank extend your security if its date becomes too short.
Before replying, redo your sums. Do your suppliers still hold their prices? Is the contract still profitable at this amount? Never leave a request unanswered, because your bid may drop out without you having decided it.
Reading a provisional award
The provisional award, sometimes published as an award notice, is the decision of the committee or the competent authority before the contract is signed. It usually opens a period during which bidders can challenge it, before any signature.
Depending on the country, it appears in the procurement journal, on the public portal or on the buyer's website, and bidders sometimes receive a letter. Read it carefully:
- The winner's name and the amount. Compare with what was read at opening. A difference may be explained by a correction, or give you a question to ask.
- The lot. Check that it really is yours.
- The time limits. Write down the publication or receipt date at once: it is often what starts the clock for an appeal. See Challenge a decision.
- The grounds for rejection, when they are given.
A provisional award is not yet a contract. If you are selected, do not start anything or buy anything before notification and the steps that follow. They are described in Deliver the contract and get paid.
- After control in advance, the authority informs the winner within 2 working days and, at the same time, the other candidates of the reasons for rejection, the contract amount and the winner's name; it publishes the report in a newspaper. It returns the guarantee to unsuccessful candidates. An unsuccessful bidder can obtain a copy of the award report within 7 calendar days of a written request (art. 37 to 39, 115; order no. 0019, art. 14).[1][4]
- The contract is signed only after the appeal period: 5 working days without a prior appeal; at least 15 working days after notification if a prior appeal was filed, until the CRD decides if needed. It must then be approved within 7 working days of the approving authority receiving the file and within the bid's validity, then notified within 3 working days. A contract that is not approved is void. A final award notice is published within 15 days after entry into force (art. 115 to 119; order no. 0019, art. 15 to 19).[1][4]
- The authority may declare the tender unsuccessful or not proceed, by reasoned decision, and informs all candidates (art. 40, 110). The winner may be asked to reconfirm its qualifications before signing (art. 116).[1]
Always ask why you were rejected
If you lose, write to the buyer to ask why. Do this even if you do not plan to challenge anything. In most public contracts and with funders, you can obtain at least the reasons your bid was rejected, and some organisations offer a debriefing. A private company often owes you nothing, but a polite request costs little.
An answer does three things. You learn whether you fell on a document, on the technical side or on price. You fix that point for the next bid. And if the reason does not match what the file says, you have something concrete, provided you act in time. A short letter is enough: the notice reference, the lot, your request and nothing else.
Read next
- Challenge a decision: appeals and time limitsWhen and how to challenge a notice or an award, before whom, and the time limits in your country that end your right to do so.
- Deliver the contract and get paidFrom notification to acceptance: start order, advance, payment certificates, penalties, late payment and what you can do about it.